News Ruien-Chièvres
No results found
-
18 October 2024
Work in front of Chièvres substation
On 21 October, Equans will begin directional drilling in Chemin du Bois Dérodé, in front of Chièvres substation. -
16 October 2024
Work on the N60 for the laying of a new underground power line
From 21 October, contractor Equans will begin directional drilling for the installation of a new underground power line in Frasnes-lez-Anvaing, specifically in Chaussée de Leuze (N60), near Rue Bas doux. -
04 October 2024
New sections in progress
Construction of a number of new power-line sections began on Monday 30 September 2024.
-
06 September 2024
Work on hold temporarily
This spring, work on the underground cable between Ruien and Chièvres was put on hold. The reason for this: several bentonite outbreaks. Elia deeply regrets these incidents and is looking into alternative working methods.
-
06 March 2024
Elia restarts works on underground cable in Kluisbergen
High-voltage system operator Elia today restarted works on the laying of the underground cable between Ruien and Chièvres. Work was halted due to a bentonite outbreak near the Scheldestraat in Kluisbergen.
-
26 February 2024
Works on Ruien-Chièvres underground cable temporarily halted by an outbreak of bentonite
High-voltage system operator Elia has halted works on the laying of the underground cable between Ruien and Chièvres due to a bentonite outbreak near the Scheldestraat in Kluisbergen.
-
11 October 2023
Underground line project kicks off
The 150 kV overhead line between the Ruien and Chièvres high-voltage substations is nearing the end of its service life. To guarantee security of supply in your region, the current line will be replaced by an underground line of the same voltage (150 kV).
-
04 September 2023
Preparations ahead of the construction phase
Now that the permit has been issued, Elia is making preparations for the construction phase, which will see the new underground connection laid before the current overhead line is dismantled.
-
20 July 2023
Display of the permit
In February 2023, the Walloon Region granted the permit for the line between Ruien and Chièvres to Elia. The municipality of Celles-en-Hainaut then lodged an appeal.
-
16 March 2023
Granting of the planning permit
The planning permit was granted in early February by the Delegated Official of Hainaut I.
-
28 September 2022
Public consultation begins
Elia officially submitted its planning permit application to the competent authorities on 22 July 2020 (with a supplement on 2 September and a file declared complete on 15 September).
-
31 May 2022
Public Utility Declaration Procedure (DUP)¹
In addition to the urban planning permit application that will be submitted shortly for the Walloon Region and the “omgevingsvergunning ” ² relating to Flanders, a demand of Declaration of Public Utility (DUP) will be filed with and examined by the Federal Public Energy Service.
-
11 March 2022
Overhead line between Thieulain and Chièvres - Audit
An audit is scheduled between Thieulain and Chièvres from 21 March to 7 April
-
23 November 2021
Environmental impact study
As part of the environmental impact study, and more specifically in connection with the dismantling of the current overhead line between the Ruien and Chièvres substations, photos must be on the territory of the municipalities involved in the project.
-
22 September 2021
September 2021 – Ruien-Chièvres project: preliminary information meeting
On 22 September, the Elia project team organised a preliminary information meeting and an online information session for members of the public.
-
01 September 2021
Advance public information meeting on 22 September 2021
The technical and administrative study period for the project to replace the high voltage line between the Ruien substation (in Flanders) and the Chièvres substation (in Wallonia) is coming to an end.