High-voltage substation Aalst
Renovation of Aalst high-voltage substation and replacement works underground 70kV connection
-
Benefits to societyElia is renovating the high-voltage substation in Aalst and replacing an obsolete high-voltage cable with a new one (70kV). This will prepare the region for energy transition and ensure the energy supply for businesses and households in the Denderstreek region.
-
Renovation of Aalst high-voltage substation
Elia is renovating the ageing high-voltage substation in Aalst and building a new GIS (Gas Insulated Switchgear) installation. In GIS installations, SF6 gas insulates the components. This makes the installation smaller and more compact than an AIS (Air Insulated Switchgear) installation. The entire site will also be integrated into the expansion of the city park. So, Elia is working on a future-oriented high-voltage substation.
You can read more about the renovation works in the news item.
-
Construction of underground 70kV connectionThe high-voltage cable between the Aalst high-voltage substation and Burchtstraat has reached the end of its service life and so, it is being replaced by a new underground cable (70kV). The new high-voltage cable (70kV) will run from the Aalst high-voltage substation in Erembodegemstraat, via De Vilanderstraat to the GIS installation in Burchtstraat.
To lay the cable, Elia is using directional drilling wherever possible to minimise disruption. In other places, work will be carried out using open trenches.
-
Environment
Elia is always mindful of the local area when carrying out works. The high-voltage system operator takes a range of measures intended to mitigate disruption and impact on the local area.
- Work will only take place during the day, between 7 a.m. and 7 p.m.
- Elia guarantees that homes and businesses will always be accessible during the works.
- If local residents are set to experience a temporary increase in disruption for a specific reason, Elia or its subcontractor(s) will always individually notify those affected.
- If normal traffic has to be diverted, the diversions will be agreed with the road authority and clearly communicated to local residents.
- Once work is complete, the land is always restored to its original state.
-
Schedule
- Commissioning of Aalst high-voltage substation: early 2027
- Start of cable works: end of May 2024
- End of cable works: beginning of September 2024
-
Documents
News
High-voltage substation Aalst
06 June 2024
Elia replacing outdated high-voltage cables with one new cable
On 10 June 2024, Elia will start works to replace a number of outdated underground cables. These works will cause some traffic disruption around the Erembodegemstraat in the summer months.
High-voltage substation Aalst
11 December 2023
Pupils play ElectriCITY game during school visit in Aalst
During the school visit on Friday, 8 December, pupils from the 5th and 6th years of primary school SAB in Aalst played the ElectriCITY game. Through this game, pupils come into contact with the complex topic of energy transition in a playful and interactive way. It was an exciting and instructive morning.
Contact us
If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.