News Mercator-Bruegel

  • 24 October 2024

    The Mercator-Bruegel project enters its final phase

    Elia is currently reinforcing the high-voltage line (380 kV) between the Mercator (Kruibeke) and Bruegel (Dilbeek) high-voltage substations. Last week, the first section of the reinforced high-voltage line between Mercator and Buggenhout was put into service. The final phase of the project will now start and involve the reinforcement of the section of high-voltage line between Buggenhout and Bruegel.
  • 06 August 2024

    E40 closure during night works

    We are currently reinforcing the high-voltage line (380kV) between the Mercator (Kruibeke) and Bruegel (Dilbeek) high-voltage substations. To remove the old conductors, the E40 near Bekkerzeel (Asse) will be temporarily closed during the night of 12-13 SeptemberThe road will be closed twice for 30 minutes, with one hour between the start of the first and second blocks. During those times, there will be no traffic at the level of the works.

  • 16 April 2024

    Pulling of Mercator-Bruegel conductors well under way

    The Mercator-Bruegel high-voltage line is currently being fitted with HTLS conductors as part of our grid backbone upgrade. These conductors, which can carry more electricity, are now being installed in the municipality of Buggenhout. Once this process is complete, work will continue in the direction of the Mercator high-voltage substation in Kruibeke via Bornem. These works are completely on track.

  • 03 October 2023

    New environmental permit for the Mercator-Bruegel project

    On 15 June this year, an appeal by local residents prompted the Flemish Council for Permit Disputes (Raad voor Vergunningsbetwistingen) to quash the permit issued for the reinforcement of the Mercator-Bruegel high-voltage line. 

     
  • 06 July 2023

    Mercator-Bruegel works temporarily on hold between Buggenhout and Dilbeek 

    Following an appeal by local residents against the reinforcement of the Mercator-Bruegel high-voltage line, the Flemish Council for Licence Disputes (Raad voor Vergunningsbetwistingen) decided on 15 June to put the permit for the project on hold

  • 24 April 2023

    Elia demolishes two 70-tonne high-voltage pylons in Bornem and Puurs-Sint-Amands

    Since April 2022, Elia has been working on the line between the “Mercator” high-voltage substation in Kruibeke and the “Bruegel” high-voltage substation in Dilbeek. Currently, the high-voltage grid operator is carrying out works in the municipalities of Bornem and Puurs-Sint-Amands. 

  • 28 March 2023

    Protective frames over N16 and railway Mechelen - Sint-Niklaas

    Elia is currently replacing a pylon in the municipality of Bornem as part of the Mercator-Bruegel project. In order to ensure that these works are carried out safely, Elia is placing protective frames over the busy N16 regional road between Mechelen and Sint-Niklaas and the railway that connects these same cities..

  • 18 July 2022

    Work at high altitude in Temse and Bornem

    Elia is currently replacing the mast arms of two existing high-voltage pylons in Temse and Bornem. This is taking place at a height of 130 metres. The work is part of the upgrade of the existing high-voltage line (380kV) between Kruibeke and Dilbeek and is necessary for the energy transition. The work will take about two weeks. Follow the works on the high-voltage line and pylons via the interactive map.

  • 25 May 2022

    Follow the works on an interactive map

    You can follow the work on this map.
  • 20 April 2022

    Start of reinforcement of high-voltage line between Kruibeke and Dilbeek

    The Flemish Government has granted the permit for Elia’s ‘Mercator-Bruegel’ project. This project involves Elia reinforcing the existing high-voltage line between high-voltage substations ‘Mercator’ in Kruibeke and ‘Bruegel’ in Dilbeek. The high-voltage line is being equipped with a new type of electricity cable that can transport more electricity. The completion of the work is planned for the end of 2026.

  • 24 January 2022

    New public consultation launched on the environmental permit

    Elia applied for an environmental permit and organised a public consultation at the end of 2021. However, at the request of the Agentschap voor Natuur en Bos (ANB), the Flemish government agency responsible for nature and forests, an additional justification was added to the environmental impact report (EIR), meaning that the whole process had to start again from the beginning. 
  • 03 November 2021

    Why is this project needed? 

    Elia wants to upgrade a high-voltage line running through the municipalities of Kruibeke, Temse, Bornem, Puurs-Sint-Amands, Buggenhout, Londerzeel, Merchtem, Asse and Dilbeek. This line forms the north-south axis of our grid. 

  • 03 November 2021

    What kind of work will Elia do?

    Elia wants to upgrade a high-voltage line running through the municipalities of Kruibeke, Temse, Bornem, Puurs-Sint-Amands, Buggenhout, Londerzeel, Merchtem, Asse and Dilbeek. This line will be equipped with a new type of conductor that can transmit more power.

  • 03 November 2021

    Why can't the high-voltage line be laid underground?

    Elia wants to upgrade a high-voltage line running through the municipalities of Kruibeke, Temse, Bornem, Puurs-Sint-Amands, Buggenhout, Londerzeel, Merchtem, Asse and Dilbeek. In light of the energy transition, this line will have to be able to transmit more electricity in the future.

  • 03 November 2021

    What impact will this have on the surrounding area?

    Elia wants to upgrade a high-voltage line running through the municipalities of Kruibeke, Temse, Bornem, Puurs-Sint-Amands, Buggenhout, Londerzeel, Merchtem, Asse and Dilbeek.

  • 08 February 2021

    Watch the video of the digital information session 

    On Tuesday 2 February 2021, Elia organised a digital information session about the Mercator-Bruegel project.

  • 20 January 2021

    Digital information moment to inform local residents

    Elia is upgrading the north-south axis of the Belgian power grid between the Mercator substation in Kruibeke and the Bruegel substation in Dilbeek. To inform local residents about the project and the works, Elia is organizing a digital information event on Tuesday 2 February 2021.

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.