Bas-Warneton-Wevelgem
Laying a new underground electricity cable and dismantling the existing overhead power line in Comines-Warneton, Wervik, Menen and Wevelgem.

Upgrading and expanding the 150-kV high-voltage grid in Comines-Warneton, Wervik, Menen and Wevelgem
Elia wants to further develop the high-voltage grid in the area around Wevelgem and Comines-Warneton. A strong and local high-voltage grid (150 kV) is essential to guarantee a reliable power supply for businesses and households in the area.
-
Benefits to society
-
The route
-
Environment
-
Schedule
-
Documents
News

04 August 2023
Work on schedule
Work on the Neerwaasten-Wevelgem project is progressing well and is on schedule. Because of this, traffic lights on the N58 can be removed next week and the road released for normal use.

20 May 2022
Laying of underground electricity cables
Elia will start laying underground electricity cables (150kV) on Chemin de la Forge and Cornet d’en Haut as from 9 May 2022. The end of the works is planned for the start of July 2022. During the works, a changed traffic situation applies.

27 April 2022
Start of laying of underground electricity cables
In early May 2022, Elia will start laying underground electricity cables (150 kV) between the Bas-Warneton (Neerwaasten) high-voltage substation and Wevelgem. Work is needed to continue to ensure a reliable supply of electricity for businesses and citizens.