Start of laying of underground electricity cables
In early May 2022, Elia will start laying underground electricity cables (150 kV) between the Bas-Warneton (Neerwaasten) high-voltage substation and Wevelgem. Work is needed to continue to ensure a reliable supply of electricity for businesses and citizens.
Work in phases
Elia will start laying underground electricity cables between the Bas-Warneton high-voltage substation in Bas-Warneton and Wevelgem in early May 2022. The works will start in the Walloon Region. For the Flemish Region, the permit application is currently pending. The works are carried out in various phases to limit inconvenience in time and space. The works will last until the end of 2022, after which the project will continue in Flanders. The map below provides an overview of the site planning.