Brabo III

Facilitating the import and export of electricity

Banner

Making it easier to transmit electricity within Belgium and trade power with the Netherlands

The Brabo project consists of three subprojects. Brabo I is already operational. Brabo II was commissioned in 2021. Work on Brabo III is now underway with a view to commissioning by summer 2026 – will enhance electricity transmission within Belgium and make it easier to trade power with the Netherlands.

  • texteIn the interest of society

    Elia’s aim with the Brabo project is to enable a transition to sustainable, reliable and affordable electricity by facilitating the import and export of electricity between Belgium and the Netherlands. The project serves three main purposes:

    • Trading power with neighbouring countries
      The Brabo project will facilitate the import and export of electricity between Belgium and the Netherlands. The development of robust power connections between countries is a key building block for an efficient European electricity market.
    • Upgrading the Belgian electricity grid
      Brabo III will see Elia upgrade Belgium’s existing 380-kV network, which forms the backbone of the Belgian power grid. Once the work is complete, Elia will be able to transmit up to 20% more electricity on the upgraded power connection within the 380-kV network.
    • Efficiently staggering electricity flows
      Renewable energy being generated around the country means an increase in flows of electricity on the power grid. Brabo III will make it easier for Elia to stagger and transmit these flows in the future.
  • texteThe route

    Brabo III can be subdivided into three parts based in Beveren, Kruibeke and Zwijndrecht.

    1. Laying a 150-kV underground cable between Kallo and Fort Sint-Filips
      Elia is laying a new 150-kV underground cable between the Kallo and Fort Sint-Filips high-voltage substations so that work can be done on the Liefkenshoek-Mercator high-voltage line at the Kallo high-voltage substation.
    2. Laying a 150-kV underground cable between Kallo and Beveren-Waas
      Elia is laying a new 150-kV underground cable between the Kallo and Beveren-Waas high-voltage substations. This is vital for maintaining sufficient capacity at 150 kV while work is being performed on the Liefkenshoek-Mercator high-voltage line.
    3. Upgrading the Liefkenshoek-Mercator high-voltage overhead line (start of works August 2023)
      Elia is taking down the existing 150-kV high-voltage line between Liefkenshoek and the Mercator high-voltage substation in Kruibeke, then erecting a new, upgraded 380-kV high-voltage line in the same location. The new high-voltage line will be a key link in the Belgian power grid.
  • environnementEnvironment

    Project EIA

    A project EIA has been carried out to gauge the environmental impact of the entire Brabo route, from Zandvliet to Mercator. The EIA determined the type, height, span and location of pylons and electric wires and the working method used, and also examined electromagnetic fields. The project EIA can be found on the website of the Flemish Government’s Environmental Impact Assessment Service: www.mervlaanderen.be.
     
    Measures to minimise disruption
    As early as the design and study phase for a project’s route and implementation method, Elia is already considering how the project will affect people, the environment and the local area. With that in mind, a number of measures designed to limit disruption have been put in place for Brabo III.
     
    • 1. Elia will restore land to its original state once work is complete.
    • 2. Where possible, Elia will set up its project site depots in existing industrial zones or paved areas to reduce the impact on the local area and the natural environment.
    • 3. Elia guarantees that local residents will always be able to access their homes.
    • 4. Work will not be carried out at night, so depots and sites will not be lit up during the night.
    • 5. Site vehicles will use the shortest, safest and most accessible routes.
    • 6. Elia will use wooden gantries or cranes when removing or pulling cables close to railways, roads or other key infrastructure with a view to minimising the impact on the surrounding area.
    • 7. If normal traffic has to be diverted, the diversions will be agreed with the relevant road authority (the municipal council or the Flemish Region) and clearly communicated to local residents.
  • Schedule

    According to the current schedule, Elia plans to start renewing and reinforcing the existing high-voltage line (150 kV) between Liefkenshoek and Mercator to a 380 kV connection as from August 2023. The end of the works is scheduled for spring 2026.

  • docInteractive map

    Brabo III route in pictures

    Elia has developed an interactive map app that can be used to visualise the Brabo III project. With the app, users can navigate between the current and future situation along the entire route. Using labels, you can navigate to a panoramic visualisation of your choice.

    The visualisations shown are intended to give an impression of the future situation; they are not binding or definitive.

    See the interactive map hereunder

    Go to https://elia.projectatlas.app/me

  • docDocuments

News

Brabo lll

06 November 2024

Highest pylon built in the Brabo III project

Last week, a new 132-metre pylon was built at the Kallosluis in Beveren. The second pylon here will follow in the next few months.

Pylon

Brabo lll

02 April 2024

Next phase begins: first pylon installed in Kallo

On 25 March, Elia installed in Kallo (Beveren) the first high-voltage pylon for the new 380-kV high-voltage Liefkenshoek–Mercator line in Kruibeke. As part of the Brabo III project, this is the first in a long line of 58 new pylons that will prepare the port of Antwerp and Waasland for the energy transition and enable our country to exchange more electricity with the Netherlands.

Pylon

Brabo lll

06 December 2023

Traffic disruption expected on E17 between Sint-Niklaas and Kruibeke due to night-time dismantling work on the high-voltage line

Elia (the system operator) is currently reinforcing the high-voltage line (380 kV) between Liefkenshoek and the Mercator high-voltage substation in Kruibeke as part of the Brabo III project. Because of this work, the E17 at slip-road complex 15 and 16 in Sint-Niklaas and Kruibeke will be closed between 11 p.m. and 4 a.m. on the night of 8 to 9 December 2023.



Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.