Site news: first section installed
At the end of January 2023, the electrical installations were successfully installed on the first section of the site (between the Rimière substation and junction 8).
Thanks to the successful collaboration between the various companies and the authorities, the project remains on schedule.
The next step: the installation of the second section, which will then be connected to the first section. After this stage, the Route du Condroz will be restored to its usual conditions.
Safety: number one priority for Elia
For the safety of road users and staff, a mobility plan has been implemented for the first two sections of the site. Do not hesitate to consult them or to follow the works on our interactive map.