Connecting the future Seraing CCGT power plant to the Elia grid
Connection of a new generation unit to Elia's grid
The project will involve laying a new 220 kV underground line connecting the future natural gas fired thermal power plant in Seraing to the Elia grid.
Although there is already a connection between the existing thermal power plant and the Elia grid, this needs to be upgraded in light of the construction of a new generation unit.
-
In the interest of societyThe ongoing energy transition means that Belgium's energy landscape is constantly evolving, both in terms of generation sources (renewables, fossil fuels, etc.) and consumption (electrification of society, new consumers, etc.). This is a far-reaching change to which all electricity market players must adapt.
As transmission system operator, Elia plays a key role in making this change a success with a view to creating a sustainable, environmentally friendly world in which to bring about the energy transition.
To ensure a successful transition, new generation units need to be connected to the high-voltage grid, and the project to lay a new underground line between the future gas-fired power plant in Seraing and the Elia grid is part of this process. -
The route
The 220-kV cables between the future Luminus CCGT power plant in Seraing and Elia's substation in Rimière (Neupré) will be laid in parallel in the same trench. The proposed route takes into account local land-related concerns and respects the environment and quality of life in the surrounding area.
-
EnvironmentCSD Ingénieurs, an independent, external consultancy approved by the Walloon Region, has been tasked with analysing the potential environmental impact of the project. The company has conducted an environmental impact assessment of the Elia project, and the assessment results have been incorporated into the planning permit application.
-
Schedule
- Advance public information meeting: 22 September 2020
- Environmental impact assessment: October – November 2020
- Submission of permit application: November 2020
- Public consultation: January 2021 – February 2021
- Application decision: June 2021
- Start of work: November 2022
- End of works: to be decided
-
Interactive map
-
Documents
News
12 September 2024
Seraing Worksite Progress Report
Please see the works progress report below:
23 August 2024
Rue des Nations-Unies in Seraing reopens for good
Contact us
If you are affected by a project and want to ask us something, please feel free to contact us.Our team would be happy to help.