- Building a new substation
A regional land-use plan (GRUP) is being drafted to build the new substation. It determines the designated use of a plot in the future and also which regulations apply. The planning process for the drafting of a GRUP consists of the following five phases:
1. The launch notice and 60-day public consultation period: the Flemish government approved the launch notice for the new substation on 28 February 2025. The public will be given the opportunity to respond to the launch notice during the public consultation period from 25 March to 23 May 2025 inclusive.
2. The scoping note: the advice and consultation responses will be incorporated into the scoping note. It sets out the location alternatives and development options to be explored and also how the environmental impact assessment will be approached.
3. Preliminary draft of the GRUP and impact reports: the environmental impact of the various alternatives has been examined and compared. The preliminary draft of the GRUP will be drawn up on the basis of all the various assessments. A plenary meeting will be organised with the advisory bodies.
4. The draft GRUP and 60-day public consultation period: the Flemish government will adopt the draft GRUP provisionally. The public will be given the opportunity to respond to the draft GRUP during the public consultation period. The consultation responses and advice will be studied, after which the GRUP will be updated if necessary.
5. Adoption of the final version of the GRUP: after the Flemish government adopts the final version of the GRUP, it will be published in the Belgian Official Gazette.
Work can start after the final approval of the GRUP about the “Substation on the Massenhoven-Van Eyck high-voltage line”. The work on the new substation will take four years to complete.
- Building a new high-voltage substation
It will not be necessary to draft a GRUP for the building of the new high-voltage substation. However, Elia will be required to submit an environmental permit application. We expect to do this in June 2026. The work is currently scheduled to start in June 2027 and take four years to complete.
- Constructing two new underground electricity connections (150 kV)
It will not be necessary to draft a GRUP for the construction of the two new underground electricity connections either. However, Elia will be required to submit an environmental permit application. We expect to do this in June 2026. The work is currently scheduled to start in June 2027 and end in 2031.