Rehabilitation of access roads following the project to reinforce the electricity connection
Works to reinforce the electricity connection between Hastière and Pondrôme substations is now complete. Following the successful commissioning of the line on 29 November, we are now embarking on the final phase of the project: the rehabilitation of the access roads to the pylons.
Schedule for restoration work
- Start of main works: 24 March 2025
- Estimated completion: end of June 2025
- Please note that some earth removal works already began on 10 March
What do these works involve?
All the roads used to access the pylons during the pylon installation and cable-laying phase will be completely rehabilitated. This step is essential for rehabilitation of the environment after the construction period.
Impact on local residents
These finishing works will be carried out with the same care to limit inconvenience to daily life. we and our subcontractors will do our utmost to minimise noise pollution and bear in mind residents’ quality of life during this period.
If you have any questions or concerns about these rehabilitation works, the project team will be happy to help you by phone on 0800 18 002 or email at: riverains@elia.be