Start of work on the Wetteren high-voltage substation

We have been working on upgrading the Wetteren high-voltage substation in Kapellendries since September.

Upgrade of the Wetteren high-voltage substation 

To ensure future security of supply, the following work is being carried out:

  • We are demolishing the existing buildings and replacing them with new, modern buildings.
  • We are erecting a new 36-kV gas-insulated switchgear (GIS) installation. A GIS installation is housed in a separate building. 
  • Fluvius is replacing the medium-voltage substation. All of the switchgear is installed here. This will enable Fluvius to continue distributing electricity to the residents of Wetteren and the surrounding area.

Phased work

The work started in September 2024 and will last three years. We are starting by demolishing the home next to the high-voltage substation (number 30, Kapellendries), before constructing the new building. We will then install and test the new installations, which will be commissioned in phases. This phased approach means that local residents will have electricity at all times during the work.

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.