Extension of works on the N975  

** Extension of works until Friday 11 April **

As previously announced, Wallonia Public Service (SPW) and the Municipality of Florennes have had to carry out work on their water piping along the N975 to resolve problems with water in the subsoil affecting our trench. This problem was preventing the good-quality compaction of our trench required for acceptance of the N975 road by SPW.

These operations have been carried out successfully. However, the duration of the works and diversions will need to be extended until Friday, 11 April, to enable us to complete the last remaining actions that had to be halted for reasons beyond our control.

Our company will then be able to resume work on 24 March to complete the following remaining work:

  • Reinforcement of a 100m-long shoulder
  • Compaction of the sub-base
  • Laying a layer of asphalt

The works underway between junctions 3 and 4 at Rue des Combattants and Rue d'Hanzinne are also continuing according to schedule.

If you have any questions or concerns about these works, the project team is available to help local residents on 0800 18 002 or by email at: riverains@elia.be

We would like to thank everyone affected by the works for their understanding and patience over the duration of this project.

The Elia project Team

 
This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.