From June 17 to September 1, 2019, Elia continues the renewal of the network in Brussels, at Avenue Charles Quint
Vivaqua and Sibelga must also intervene on this avenue, a coordination of work was carried out in order to reestablish the traffic at the beginning of the season.
This work will take place mainly on the side of even numbers, in the direction of the highway,from the Basilica to the Drève de l'Aérodrome.
Appropriate traffic has been developed to ensure the smooth running of the work safely for both road users and the site.
From June 17 to September 1, 2019, at avenue Charles Quint towards the highway:
• Traffic will be limited to one lane;
• A blockage parking ban will be introduced depending on the progress of the work;
• Everything will be done to maintain access to private garages;
• The Marguerite d'Autriche and Pampoel bus stops will remain serviced, but will be slightly displaced.
Access to homes, shops and businesses will be guaranteed all the time.