News Auvelais-Gembloux
No results found
-
28 September 2022
Dismantling of the old 70 kV connection
After 18 months of work, the installation of the new 150 kV underground connection between the Auvelais and Gembloux substations has been completed. It was successfully energised on 20 September. Now that security of supply is guaranteed, the dismantling of the old overhead line can begin in early October.
-
26 April 2021
Project to start on 26 April – use our interactive map to stay informed!
According to the provisional schedule, the project to build the first 150-kV line between the Auvelais substation and the Gembloux substation will start on 26 April 2021.
-
03 January 2021
Planning permit obtained and end of the appeal period
Following the submission of its application for a planning permit to the relevant authorities on 3 July 2020, transmission system operator Elia has now obtained the permit.
-
30 November 2020
Permission granted for underground connection
Planning permission has been awarded for the replacement of the 70-kV overhead power line between the Auvelais and Gembloux high-voltage substations with a 150-kV underground connection following a different route.
Full details of the project will follow soon.
-
03 August 2020
Public consultation begins
Elia officially submitted its planning permit application to the competent authorities on 3 July 2020. -
02 July 2020
Submission of the planning permit application
During the advance public information meeting held at Gembloux Town Hall on 21 November 2019, all residents were able to find out about the underground-line project and ask questions. The independent consultants CSD Engineers then worked on the environmental impact study . -
12 March 2020
Invitation to present the conclusions of the environmental impact study
On November 21, Elia, your high-voltage transmission system operator, organised a Preliminary Public Information Meeting. The purpose of this meeting was to inform you about the project for an underground high-voltage link between the Auvelais and Gembloux substations. -
22 November 2019
Auvelais-Gembloux: Presentation of the underground connection project
On Thursday, 21 November, Elia, the operator of Belgium's high-voltage transmission system, presented the new underground connection project linking the Auvelais and Gembloux substations. -
25 October 2019
Presentation of underground project to local residents on 21 November
Following the administrative and technical feasibility studies conducted by Elia in recent months, the transmission system operator is now inviting local residents to the preliminary public information session. -
01 October 2018
Study of underground line route continues
Last July, Elia announced its intention to carry out in-depth studies into the technical and administrative feasibility of an underground line route identified in the environmental impact study. -
02 July 2018
Presentation of a project status report
On 11 July 2018, Elia met the local authorities involved in the project aimed at renewing the HV connection between Auvelais and Gembloux.
-
01 March 2018
Auvelais-Gembloux: municipalities organise meeting between Elia and local residents
On 23 March 2018, the authorities of the town of Gembloux held an information session where Elia and engineering firm CSD Ingénieurs met with the municipal authorities and representatives of local residents impacted by the Auvelais-Gembloux project.
-
01 February 2018
Soil testing for Environmental Impact Study
As announced in November 2017, the consulting firm in charge of the Environmental Impact Study (EIS) would like to examine some aspects in further detail.