Start of works

Following the granting of planning permission on 26 July 2024, work to reinforce the Gramme-Rimière 380 kV overhead line will begin on 19 August 2024. 

It will be carried out in three main phases:

  • First, the teams will carry out reinforcement work on the pylons, including the replacement of pylon No. 2 and pylon No. 27.
  • Next, the second three-phase transmission line will be installed.
  • Finally, a line-cable transition substation will be created at the Gramme substation (in Huy).

 

What is a three-phase transmission line?

It is an electric circuit, a set of three electricity transmission conductors (commonly known as ‘cables’) that make up a three-phase overhead line.
The conductor is the element through which electricity circulates on an electrical grid. A conductor is one of the three phases of the three-phase circuit.

 

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.