150kV cables in Scheldelaan
Under the planned work schedule, Elia was due to complete its work on laying two 150kV cables in Scheldelaan by the end of spring 2018. However, during the cables' test phase problems were encountered in the junction box pits, where the two sections of cable are attached to each other. In the light of these problems, Elia decided to redo all the cables' junction boxes.