News Mortsel-Agfa-Gevaert
No results found
-
19 August 2022
Last phase of works in August
Over the last month, Elia has been working on the renovation of the road surface after the works for new underground cables between the “Mortsel” high-voltage substation and the company Agfa-Gevaert. At the end of August, the works will come to an end and the signposting will be removed.
-
03 May 2022
Definitive road repair of the streets concerned in Mortsel
In recent months, Elia has installed new underground electricity cables (15kV) between the “Mortsel” high-voltage substation and the company Agfa-Gevaert. Now that the laying of the electricity cables has been completed, the contractor Scheldekabel NV is renewing the road on behalf of Elia and the city of Mortsel.
-
10 August 2021
Work to lay underground cables begins in Heirbaan and Drabstraat
Elia will begin laying underground electric cables in Heirbaan and Drabstraat on 9 August 2021. As a result, traffic rules will be temporarily modified in both streets.
-
02 July 2021
Elia begins laying underground cables (15 kV) in Osylei
Elia plans to install new underground electric cables (15 kV) between the Mortsel high-voltage substation in Drabstraat and the Agfa-Gevaert industrial site in Septestraat in Mortsel. This work is necessary in order to continue guaranteeing a reliable supply of electricity for Agfa-Gevaert.
-
01 July 2021
Elia starts laying underground power cables (15 kV) in IJzerenweglei
Scheldekabel NV is starting work on laying underground power cables (15 kV) in IJzerenweglei for Elia, the operator of Belgium's high-voltage grid. Elia plans to lay these cables between the Mortsel high-voltage substation in Drabstraat and the Agfa-Gevaert site in Septestraat, with a view to ensuring that Elia can continue guaranteeing a reliable electricity supply for Agfa-Gevaert in the future.
-
15 June 2021
Laying of underground cables begins in Septestraat
Elia will start laying underground electricity cables in Septestraat on Monday 21 June.
-
12 June 2021
Restoration of road surface on Ter Varentstraat and start of work on Bloemenlei
Elia is restoring the road surface and completing the work on Ter Varentstraat in Mortsel. Starting on 9 June, the worksite will move towards Agfa-Gevaert and Elia will start laying underground cables in Bloemenlei.